Media Center

GAIA Wind Power Plant (WPP) Project – Ula / Muğla

As of February 16, 2026, we have officially commenced our work on the GAIA WPP Project. Within the scope of the project, crane installation services for a total of 7 wind turbines are being carried out by our company.

In this regard, the installation of two turbines has been successfully completed, and operations on the third turbine are currently underway as planned. All of our on-site operations are being carried out meticulously in line with our high occupational safety standards and engineering expertise.

Self-Owned Lifting and Transport Equipment Used in the Project
  • LR 1700 – 700-ton capacity main lifting crane
  • LTM 1230 – 230-ton capacity auxiliary crane
  • 1 x 8-axle trailer for pad-to-pad transport operations
  • 160-ton capacity mobile crane
  • 1 x 4-ton capacity Manitou telescopic handler

Thanks to this strong equipment fleet, maximum efficiency, precision, and operational continuity are ensured on site.

Turbine Model We Provide Services For: ENERCON E-138 EP3

The turbine model installed at the GAIA RES site is the ENERCON E-138 EP3, a high-efficiency wind turbine developed for medium wind conditions.

  • Rated power: 4.26 MW
  • Rotor diameter: 138 m
  • Swept area: 15,011 m²
  • Wind class (IEC): II A
  • Cut-out wind speed: 28 m/s
  • Cut-in wind speed: 2.5 m/s
  • Tower options: 81 m, 99 m, 111 m, 131 m, 160 m
  • Turbine concept: Gearless, variable-speed, full-scale converter system
  • Operating temperature range: -25 °C / +40 °C (extended: -40 °C / +50 °C)

Contact Us Now...